CIC starts on site at the Holiday Inn Aylesbury

Home > Updates and Insights > CIC starts on site at the Holiday Inn Aylesbury

6 month refurbishment project begins

We are delighted to have started on site at the Holiday Inn Aylesbury. Over the next 6 months, we will be refurbishing 139 rooms including the bathrooms and corridors, across a programme of 4 phases managed by our Site Manager, Victor. The refurbishment mirrors the concept previously rolled out at the Holiday Inn, Eastleigh.

Our work includes:

  • New carpets and decorations throughout rooms and corridors.
  • New ceilings fitted throughout corridors
  • New double and single doors through the corridors inlcuding all new ironmongery
  • An upgrade of some sanitaryware to some bathrooms – new taps, toilet seats, shower screens, bath panels, showers, basins, baths and vanity units.
  • The fitting of new case goods in each room, new wardrobes, headbaords, desks, TV panels.
  • Installation of new lights
  • Installation of sofa beds and  beds
  • Fitting of new mirrors & artwork
  • Upgrade of air-con throughout

We are specialists in working in live trading environments, ensuring that hotels remain open throughout their refurbishments.  If you have a hotel refurbishment you would like us to price then please get in touch.

Creative Interior Contracts
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.